I'm trying to test the lead date calculation for an item on a purchase order. On the level of the Item card, the Lead time is set up as 10 days, safety time - as 15 days.
The line of the purchase order does not calculate the planned receipt data and expected receipt data even so the page inspection shows that the date formulas are in:
Interesting is that this works perfectly well in Sandbox and does not work in UAT. Both environments are updated at the same time.
What can be the reason?