When trying to update a production order with an Item which has a route with wait time AND send-ahead, then the calculation needs too much calendar from the work center with wait time and send-ahead. It seems when calculating forward BC needs the wait time for each send-ahead. That is if we produce 100 with wait time 1440 minutes and a send-ahead of 50 then BC needs 20 days in the calendar to calculate forward even though when finished the wait time is still only a day (of course depending on the run time).
This only happens if I calculate forward. And only if the line before on the route also has send-ahead.
There is no problems when calculating backwards.
This seems to be a bug which would be nice to have fixed... :)
I have tried this on latest build online.