Finished Production Order - Date

Posted on by 100

Hi , 

I am trying to figure out how the finished date is populated in Finished Production Order. Can someone help me with this?

pastedimage1673554846588v1.png

  • Verified answer
    SV1 Profile Picture
    SV1 100 on at
    RE: Finished Production Order - Date

    Thank you for the detailed explanation. This really helped

  • Suggested answer
    Ron.McV Profile Picture
    Ron.McV 98 on at
    RE: Finished Production Order - Date

    Agreed, very good answer and screenshots to illistrations, too.

  • Suggested answer
    YUN ZHU Profile Picture
    YUN ZHU 64,134 Super User on at
    RE: Finished Production Order - Date

    Hi, Generally, the Posting Date when you modify the status will be automatically used as the Finished Date.

    For example,

    pastedimage1673565986991v1.png

    pastedimage1673566003076v2.png

    pastedimage1673566066459v3.png

    Hope this helps.

    Thanks.

    ZHU

  • Suggested answer
    Inge M. Bruvik Profile Picture
    Inge M. Bruvik 32,720 Super User on at
    RE: Finished Production Order - Date

    I think that is the workdate you have in your system at the time you set your production order to status finished.

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,989 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,588 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans