reorder point planning ignored POs before planning start date

Posted on by 219
Hi experts:
 
I 'm using reorder point for planning, and have a purchase order with 'expected receipt date' before the 'planning start date',
when I submit the planning worksheet , this supply appeared to be ignored by the system.
 
 
Not sure if this is stand functionality of Business Central? thanks.
 
Regards,
Lanqing.
Categories:
  • Suggested answer
    Shauna Langley Profile Picture
    Shauna Langley 691 Super User 2024 Season 2 on at
    reorder point planning ignored POs before planning start date
    Hi,
     
    I tried an item with the same setup as you have.  Purchase order with expected receipt date as below.  Item currently has not inventory and no demand.
     
     
    Item has the following setup.
     
     
    When I run the planning worksheet I do not get anything suggested using the following:
     
     
    Have you got demand that will use the quantity on purchase order which is why it needs more?
     
    Try using the item availability to check demand and supply.
     
     
    Hope that helps,
    Shauna
     
     
  • qjwlq Profile Picture
    qjwlq 219 on at
    reorder point planning ignored POs before planning start date
    Hi, Shauna:
     
    Thanks for the reply.
     
    I'm using reorder point instead of lot-for-lot, so the lot-for-lot options you mentioned are all grey out.
     
  • Suggested answer
    Shauna Langley Profile Picture
    Shauna Langley 691 Super User 2024 Season 2 on at
    reorder point planning ignored POs before planning start date
    Hi,
     
    Do you currently have stock keeping units setup?  There is field on here to Include Inventory which should be ticked.
     
     
    I would usually switch this on and then change the Re-ordering Policy to what you need.
     
    Hope that helps,
    Shauna
  • qjwlq Profile Picture
    qjwlq 219 on at
    reorder point planning ignored POs before planning start date
    Design details say: All supply and demand before the starting date of the planning period will be considered a part of inventory or shipped.
     
    but not sure why is not working for me.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans