Posting the Production Journal?

Posted on by 3,482

Hi:

After finishing a Released Production Order without even opening or posting its Production Journal, I have noticed that posting to the Item Ledger, Capacity Ledger, and the General Ledger still occurs.

My manufacturing environment is set to Backward Flush everything.

Is posting the Production Journal really necessary?

Thanks!

John

  • Verified answer
    Ben Baxter Profile Picture
    Ben Baxter 4,892 Super User 2024 Season 2 on at
    RE: Posting the Production Journal?

    Yes, if you Components and Routing Work/Machine Centers are all set to be backward flushed.  You can create and immediately finish the production order and BC will consume the BOM, output the finished good, and post capacity cost as outlined in your BOM/Routing.  Essentially a fully automatic production process assuming a perfect world and no variance.

  • Suggested answer
    Andy Sather Profile Picture
    Andy Sather on at
    RE: Posting the Production Journal?

    Hello John,

    If you don't get further responses to this issue, you may want to raise a support request to Microsoft support via your CSP / Partner.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

New! Quick response templatesâš¡

Save time with the new custom templates!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,188 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,030 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans