Posted on by 1,340

Hello,

I have a client that setup 2012 as 01/01/2013 through 12/31/2013.

How can I correc this?  Did I mention they are on Great Plains 7.5?

 

*This post is locked for comments

I have the same question (0)
  • Richard Wheeler Profile Picture
    75,852 Moderator on at

    You can simply go back to Setup->Company->Fiscal Periods and change the dates to 01/01/2012-12/31/2012 and then go to Utilities->Financial->Reconcile.

    Now hopefully they have not posted anything into those periods. That would be a separate issue with which to deal.

  • Jason Buckingham Profile Picture
    1,340 on at

    Thanks for the reply,

    We tried that and got "This date is not in the fiscal year".  We tried this in the starting date and got the error then for each fiscal period and got the same error.

    There was one GL transaction for 2012 that they tried to post.  It posted to 12/31/2010 which is the last day of the most recent closed year.

  • Richard Wheeler Profile Picture
    75,852 Moderator on at

    OK, that makes sense since 2012 was defined as 01/01/13-12/31/13. Can you reverse that one entry that went to 2010?. Change the dates on FY 2012 and run reconcile. After you do that you should be able to post into 2012 with 2012 dates.

  • Jason Buckingham Profile Picture
    1,340 on at

    Thank you,

    My issue now is that I cannot change the dates on FY2012 becasue of the error I mentioned. "This date is not in the fiscal year."  I cannot manually change the dates in the fiscal period setup window.

  • Richard Wheeler Profile Picture
    75,852 Moderator on at

    You should be able to change this date and then click Calculate. Do not try to change the individual dates.

     

  • Jason Buckingham Profile Picture
    1,340 on at

    Still cannot:

    "The date cannot be part of a different fiscal year"

     

  • Richard Wheeler Profile Picture
    75,852 Moderator on at

    Now I see what is the problem.

    Step 1) Wait until all users have exited this company

    Step 2) Backup your company database

    Step 3) Run these scripts against your company database

    delete sy40100

    where year1=2012

    delete SY40101

    where YEAR1=2012

    Step 4) Go back to Setup->Company->Fiscal Periods and set up FY 2012 with the correct dates

    Step 5) Run Utilities->Financial->Reconcile.

    You will still have that one J/E that went into 2010 to offset.

  • Richard Wheeler Profile Picture
    75,852 Moderator on at

    You may also need to add

    delete sy40102

    where year1=2012

    delete SY40103

    where YEAR1=2012

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics GP (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans