Resource availability not showing

(0) ShareShare
ReportReport
Posted on by
I setup a route for a demo and have a resource that is showing as available on one operation and not the other. Both operations have the same resource requirement and same setup. The resource is not set to finite capacity. I am unable to schedule a production order because of this issue. See the screenshots for the comparison. 
I'm bewildered. Thoughts?
 
 
 
 
 
 
I have the same question (0)
  • Suggested answer
    Hana Xue Profile Picture
    Microsoft Employee on at
    Hi,
    By querying relevant documents, you can define multiple requirements on a routing, but the resource type you define must be consistent with other requirements.
    For example, you cannot define one requirement for a resource of the type Tool, and then define a second requirement for a skill, because a tool cannot have a skill. The correct resource type is Human resources, because human resources can have skills.
    You can, however, define requirements that take into account potential changes in the future. For example, you can first define a resource group, and then define a resource that is not presently a member of that resource group. You only get an error if the resource is not a member of the resource group when the production is planned. This is because resources can be moved from one resource group to another after requirements have been defined.
    Since the resource is not a member of the resource group when production is scheduled, it shows the same problem as yours:


    Thanks!
    Best Regards,
    Hana
     
     
  • Suggested answer
    Anurag Profile Picture
    4 on at
    Hi, 
     
    Please verify whether the resource is linked to the calendar or not. Also, shift is assigned to the calendar or not.
     
    Regadrs,
    Anurag Tripathi 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Mallesh Deshapaga Profile Picture

Mallesh Deshapaga 1,066

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 212 Super User 2026 Season 1

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 136 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans