Master planning and Waiting time after production

(0) ShareShare
ReportReport
Posted on by 38
Dear community,

After our production process, for some production orders, not all, we need to wait quite some time for lab tests to return before we can ship to customers.
Obviously, we can use quality orders for issuing those lab test; no worry in that respect.
But my challenge is to include this waiting time in the masterplan and therefore suggest production orders at the right time.
Does anyone have any idea how to do that?
I have the same question (0)
  • Verified answer
    Laurens vd Tang Profile Picture
    4,394 Super User 2026 Season 1 on at
    Hi Janco,
     
    I believe you can use the setting "transit time" for it. 
     
     
     
    Best regards,
    Laurens van der Tang
  • Janco van Dijk Profile Picture
    38 on at
    Hi Laurens,

    That looks promising.
    Will definitely try whether that does it.

    Thanks,
    Janco

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Mallesh Deshapaga Profile Picture

Mallesh Deshapaga 1,093

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 193 Super User 2026 Season 1

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 148 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans