2 Demand forecast lines are created with the following requirement date.
1) 24/05/2024
2) 5/07/2024
We are using the planning optimization after master plan was executed.
1) Planned production order 1 was created with the requirement date of 19/05/2024 for the demand forecast line requirement date '24/05/2024 that is working as expected.
2) Planned production order was also created with the requirement date of 19/05/2024 for the demand forecast line requirement date '5/07/2024. We have a lead time of 20 days, but the requirement date is pushing to 35 days.