Supply chain | Supply Chain Management, Commerce
Unanswered

Freeze Time Fence

(0) ShareShare
ReportReport
Posted on by 20

Hi;

My experience in other MRP systems (SAP and Oracle) is that when applying a time fence on a SKU a planned order can still be manually manipulated within that time fence, or a planned order outside of the time fence can be manually pulled forward into the "frozen" period.

We have a need to do that in D365 but when we try to move an unprocessed planned order into the Freeze Time fence period we get an error that states "The order delivery date is within the freezing fence.  The first date out of the freezing time fence is" then the date of our freeze time fence + 1.

Is there some background configuration in the freeze time fence that we can change to allow this?  Is there some other time fence we should be using?  Something else we might be doing wrong?

Thanks!

-Phil

I have the same question (0)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Mallesh Deshapaga Profile Picture

Mallesh Deshapaga 296

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 234 Super User 2026 Season 1

#3
Syed Haris Shah Profile Picture

Syed Haris Shah 139 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans