Is There a Way to Ignore Past Due Demand in Master Planning(AX 2012 r2)?

(0) ShareShare
ReportReport
Posted on by 26

We have added a column to the Sales Line table that allows us to control the "release" of the SO demand to our product departments, most of our products are made or purchased to order.  Our product departments won't process the SO unless is has a current requested ship date, so with all that said AX Master Planning doesn't know about our added release field.  Master planning is only partially updating coverage because of lack of capacity due to all the past due demand.  I would like MP to ignore the past due SO lines.  Is there a parameter on the coverage group that would allow me to ignore this past due demand?

I have the same question (0)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Microsoft Dynamics 365 | Integration, Dataverse, and general topics

#1
Martin Dráb Profile Picture

Martin Dráb 45 Most Valuable Professional

#2
iampranjal Profile Picture

iampranjal 36

#3
Satyam Prakash Profile Picture

Satyam Prakash 31

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans