I am looking for a way to set up a routing with multiple operations (CLEAN, PAINT, BAKE). For the CLEAN & PAINT Operations, the Run time is applied to each individual unit (i.e. 10 mins per unit). However, the parts go to BAKE Operation, all units will be placed in the oven at once for 60 minutes. When review against a calendar, I cannot figure out how to set the BAKE operation to apply to ALL units within the Lot (still scheduling as each). I am unsure if this is a Machine Center vs Work Center issue or if this is a field I am missing to set Run Time as Per Lot instead of Per Unit.