Hi
I've created an intercompany setup for the following example:
Comp A buys product X from comp B and sells to Customer. Min stock level of item X is defined for comp A and lead time is defined between companies A and B as 5 days. Intercompany group is defined incl companies A and B, each company has another company set in Master Plan in Downstream Plans. Intercompany plan is started having 2 iterations defined. As result - after planning - a planned production order in comp B is delayed e.g. 30 days but when we turn to related planned purchase order in comp A - here we can see only 5 days of delay (caused by LT). Why whole delay calculated in comp B is NOT transferred to comp A ?
Any suggestions kindly appreciated
Witold