Dear Experts,
I have a problem when doing the PR-PO process for project procurement, where the project budget seems to be committed twice when I release approved PR to PO.
Case:
PR creation:
- You create a PR for 1.7M worth of Big Tree.
- PR is approved → 1.7M is committed to the budget.
PR Release to PO:
- Vendor is selected during release.
- System generates conflicting messages:
- PO created.
- PO creation cancelled due to errors.
- Budget not adjusted correctly.
- Budget exceeded by 400K → implies 3.4M committed, which is double the PR amount.
PO Processing:
- PO is approved and confirmed.
- Budget control check passes.
- Product receipt and invoice are posted.
- Budget status shows committed amount is now consumed.
Please help me with this case. Although the PO is proceeded as usual, but it may confuse users with these messages.
Thanks in advance.
Regards,
P