Gantt Chart and production calendar

(0) ShareShare
ReportReport
Posted on by 15

Hello All ,

Our production calendar is set as Monday to Thursday 24 hours open , and Saturday + Sunday close.

The issue is the Gantt chart isn't blocked at those days , so planners can schedule production orders on Sunday for example.

 Any tips how can I solve this?

Thanks

  • Lennart Lauterbach Profile Picture
    75 on at
    RE: Gantt Chart and production calendar

    Glad to hear that! If this helped you, I'd appreciate it if you'd mark this as a Verified Answer, which may in turn help others as well.

  • Ohad Atias Profile Picture
    15 on at
    RE: Gantt Chart and production calendar

    Hi Lennart ,

    thank you so much!!

    problem solved !

    Ohad

  • Suggested answer
    Lennart Lauterbach Profile Picture
    75 on at
    RE: Gantt Chart and production calendar

    We've had the same issue before. Gantt chart ignored our defined working times and open calendar days.Solution was to tick the check box "Working time" in Cost Management -> Manufacturing accounting policies setup -> Route groups

    pastedimage1654076516371v1.png

    Hope this helps to solve your problem!

  • Oleksiy  Khoroshylov Profile Picture
    1,745 User Group Leader on at
    RE: Gantt Chart and production calendar

    I assume the lower section with actual working times is blank for these "closed" days. Is that calendar assigned to production resource with type machine and the system is still scheduling production job for such resource on "closed " days? Is resource configured as finite capacity one?

  • Ohad Atias Profile Picture
    15 on at
    RE: Gantt Chart and production calendar

    Hi Oleksiy ,

    Yes , planners are checking the 'finite capacity' box - by default is on.

    1106.Capture.PNG

  • Suggested answer
    Oleksiy  Khoroshylov Profile Picture
    1,745 User Group Leader on at
    RE: Gantt Chart and production calendar

    That is strange. Can you share calendar working times screenshot? Also do you know if planners check "finite capacity" box when scheduling production orders?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge 🌸

WIN Power Platform Community Conference 2025 tickets!

Jonas ”Jones” Melgaard – Community Spotlight

We are honored to recognize Jonas "Jones" Melgaard as our April 2025…

Kudos to the March Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 294,095 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 232,866 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,158 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans