Production Formula substitute / alternative items

Posted on by 15
I have this scenario :

- If there's OH inventory on item A, use item A in the formula
- If there's no OH inventory on items A. use a phantom item B which can be produced from item c and a route 
 
I set both item A and item B to the same plan group, set priority 1 on item B and qty 1, set priority 2 on item A and no quantity 
 
The problem is with the setting above,  planning optimization still use item B although there's no inventory on item B and there's OH inventory on item A
  • Suggested answer
    ColbyGallagher Profile Picture
    ColbyGallagher 3,664 on at
    Production Formula substitute / alternative items
    Regardless of feature state in .38 or .39, If you want A to be used first, it should be priority 1 and B should be priority 2.  
  • KE-16072243-0 Profile Picture
    KE-16072243-0 15 on at
    Production Formula substitute / alternative items
    Thank you GuyUK
    I already found the solution to my issue a couple of hours ago:
    Deploy Release 10.0.39, Scheduled it for tomorrow
    Will test again after the deployment
  • Guy Terry Profile Picture
    Guy Terry 28,621 Super User 2024 Season 2 on at
    Production Formula substitute / alternative items
    Per this link, support for Plan groups was not planned for until, well, about now. But I have not read anything to say that it has actually been done.
     
    Does it work for you if the Item B item is not a phantom item?
  • KE-16072243-0 Profile Picture
    KE-16072243-0 15 on at
    Production Formula substitute / alternative items
    Hi Kevin Xia 
    I know about priority based planning, which is irrelevant to my question
    Formula priority and plan group are used together for substitution, not for master planning priority
  • Suggested answer
    Kevin Xia Profile Picture
    Kevin Xia Microsoft Employee on at
    Production Formula substitute / alternative items
    Hi,
    You can refer to this official document: Priority-based planning - Supply Chain Management | Dynamics 365 | Microsoft LearnThis article describes the priority-based planning feature of Microsoft Dynamics 365 Supply Chain Management. The feature adds support for demand-driven planning, which is one step of Demand Driven Material Requirements Planning (DDMRP). You can also refer to this official document: Optimize your supply chain with priority-based planning - Microsoft Dynamics 365 Blog. It introduces how to optimize your supply chain with priority-based planning.
    Best regards,
    Kevin

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans