Can i change the scheduled duration field of project task without changing the start and end dates?
If So how can this be achieved?
*This post is locked for comments
Hello,
Can i change the scheduled duration field of project task without changing the start and end dates?
If So how can this be achieved?
*This post is locked for comments
You are correct, the effort can be changed though (see insert).
What is the business reason for not wanting duration to reflect difference between start and end dates.
Hello Ausbiscuit,
Even when you change the task to manual, duration automatically sets to the difference between start and end dates. This is the default behaviour it seems.
Thanks.
Charith
Yes, change to manual by clicking the icon on the left of the row.
Mohamed Amine Mahmoudi