Hi There!
I'm having a bit of trouble trying to understand why the Starting Date-Time and Ending Date-time (as well as Starting and Ending Date) are displaying the following dates when I Calculate the Regenerative Plan in the Planning Worksheet:

The Lead Time and Safety Lead Time is not set for the item, so it should display the date-times as the Due Date by default.
Cheers!