Hi,
I am new to business central and we are currently undertaking UAT on the job management module.
My question involves creating budget planning lines. We generally work with fixed price contracts so I set up a billable line for invoicing.
For costs I have set up budget planning lines. These seem to work as expected until we reach a point where the cost exceeds the original budget. When a quantity is transferred/posted via a job journal which results in the original quantity being exceeded then the original quantity is changed to match the new total quantity. This seems completely wrong as it means the original budgeted quantity has changed (which shouldn't have) and it appears as if there is no variance.
What am I doing wrong?
Regards
Ross