Business Central Outsourcing productionorders - how to set the warehouse in advance for materials?

Posted on by 155

Can you help me?

I have an routingplan with a outsourced department. On the outsourcedwork center the vendor is linked. I also have a location linked there, it is a separate location (fo the vendor?)

UW1.PNG

In my routing link code (KN in this example) , I have linked the 2 material lines to the outsourced work center.

uw3.PNGuw4.PNG

When I generate the productionorder all the component lines are being set on the main location (in this example "1"). The 2 material lines for the outsourced workcenter are needed on the outsourced location (in this example "UW3"). 

uw2.PNG

How can I set up BC to set the right warehouse automatically for each component line in the production order?

Thank you in advance!!

Kind regards,

Brutus

  • Suggested answer
    Marco Mels Profile Picture
    Marco Mels on at
    RE: Business Central Outsourcing productionorders - how to set the warehouse in advance for materials?

    Hello,

    If you do not get further traction on this one, then you may want to consider raising a support ticket to Microsoft support via your CSP.

    Thanks.

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 9th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Dynamics 365 Community Newsletter - August 2024

Catch up on the latest D365 Community news

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,186 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 227,996 Super User 2024 Season 2

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans