Hi
I tried to change UOM in one of our Work Center from Minute to Hour but received this error message "Unit of Measure Code cannot be changed for scheduled work centers." how I can change UOM here?
Thanks
Mahgah,
Yes, not possible with Routing and open Prod. Order with the UOM for the Work Center set. I normally recommend to my clients to make a new Work Center. Then make sure you calculate the new UOM for Calendar and planning. Then update the Routings that used the old Work Center to new one. Not sure if this change effects your rolled-up Standard Cost but that too might be required and updated.
Hope this helps.
Thanks,
Steve
Hi Steve
Thank you
I will follow your advice.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
OussamaSabbouh 3,151
Jainam M. Kothari 1,443 Super User 2025 Season 2
YUN ZHU 1,092 Super User 2025 Season 2