Fixed and variable cost subcontract work center

Posted on by 5

Is it possible to have a subcontract work center that has a fixed cost and variable cost for a subcontract work center?     For example, a processing fee of $ 25 and then $ 1 / unit produced.

  • KasparsSemjonovs Profile Picture
    KasparsSemjonovs 3,254 Super User on at
    RE: Fixed and variable cost subcontract work center

    Add Run time for the first routing line and then try to refresh the Production order

  • Hokitika Profile Picture
    Hokitika 5 on at
    RE: Fixed and variable cost subcontract work center

    If I refresh the production order, I get a divide by zero error when the work center with only setup time is included.  This is the routing.

  • Jun Wang Profile Picture
    Jun Wang 5,517 Super User on at
    RE: Fixed and variable cost subcontract work center

    yes you can do that.

  • Hokitika Profile Picture
    Hokitika 5 on at
    RE: Fixed and variable cost subcontract work center

    Thanks for your help.

    I need to create a purchase invoice for the costs.  Otherwise, I would use a non-inventory item in the BOM with no work center.

  • Hokitika Profile Picture
    Hokitika 5 on at
    RE: Fixed and variable cost subcontract work center

    Is it possible to have a subcontract work center with only setup time as the fixed cost ?

  • KasparsSemjonovs Profile Picture
    KasparsSemjonovs 3,254 Super User on at
    RE: Fixed and variable cost subcontract work center

    That is a valid concern - this has to be tested - if the item is linked via Routing Links to the Subcontracting operation - then it could be that it is posted there, but I haven't tested this setup myself

  • Jun Wang Profile Picture
    Jun Wang 5,517 Super User on at
    RE: Fixed and variable cost subcontract work center

    my question on the other option is that the non inventory item cost, as a component, will not be posted to the subcontractor

  • Suggested answer
    KasparsSemjonovs Profile Picture
    KasparsSemjonovs 3,254 Super User on at
    RE: Fixed and variable cost subcontract work center

    Processing fee can be added a purchase line on PO. You can set it up as recurring line that is automatically added to each order, but this could make it difficult, if You have several items in each order and for each You need to pay the processing fee.


    Another option You can explore is that You add an Item of type Non-Inventory where cost is 25$. Then add it to the components of Production BOM and if needed You can add a Routing link - so that this Item is consumed only at the specific operation in your Routing. With this setup tricky part is regarding the consumption quantity - as You cannot specify in BOM that for each unit 1 processing has to be used, but I think You can provide that 0.00001 for each peace has to be used, and on the Item card provide Rounding precision of 1. This will work if You are not producing more than 99k finished product units in each production

  • Suggested answer
    Jun Wang Profile Picture
    Jun Wang 5,517 Super User on at
    RE: Fixed and variable cost subcontract work center

    I don't think you could set up that on the work center level. but when user creates purchase order for subcontractor, user could add a line as an item charge for the processing fee

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,696 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,490 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148