Requested Receipt Date Updating Automatically in Purchase Order

(5) ShareShare
ReportReport
Posted on by 66

Hi everyone,

I've noticed that when I modify the quantity in a purchase order line, the Requested receipt date sometimes updates automatically. This seems to happen when the initial requested date is within the purchase lead time entered in default order settings(30 days). However, if I manually enter a date beyond this lead time, the system doesn't overwrite it when I change the quantity.

I've checked the Procurement and Sourcing parameters, but I couldn't find any setting controlling this behavior.

Has anyone else experienced this? Is there a way to prevent the system from automatically adjusting the requested receipt date based on lead time when modifying the quantity? There is no warning message regarding this also.

If it can help we are in version 10.0.42. 

Thanks in advance for your help!

I have the same question (0)
  • Verified answer
    André Arnaud de Calavon Profile Picture
    303,716 Super User 2026 Season 1 on at
    Hi,
     
    Do you need the lead time of 30 days? If so, what you experience is the standard behavior. In case you need a different behavior, set another value for the lead time or consider a customization.
  • Emmanuelle.G Profile Picture
    66 on at
    Hello André, 
     
    Thank you for your response. I was not sure this behavior was caused by a parameter or not. Maybe we will review our purchase lead time in that case. 
     
    Thank you ! 
     
  • Suggested answer
    Laurens vd Tang Profile Picture
    4,606 Super User 2026 Season 1 on at

    Good day,

    You can turn it off via the purchase trade agreement using the 'Disregard lead time' parameter.

     
     
    The main disadvantage is that Master Planning will also ignore the lead time, and you won’t see the lead time on the purchase order anymore.
     
    Best regards,
    Laurens van der Tang

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Mallesh Deshapaga Profile Picture

Mallesh Deshapaga 254

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 192 Super User 2026 Season 1

#3
Syed Haris Shah Profile Picture

Syed Haris Shah 137 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans