Here is three scenario which i want to cater,
If the difference of shipment and expected receipt date is 14 days then those lines should not appear in planning worksheet.
If its then after that 14 days till more 45 days it should suggest rescheduling the order .
At last it would be the regular behavior cancel and new.
How this can be achieved in reordering policy lot for lot and also after explaining all theses in detail let me know how and what impacts will be there when dampener is defined 14 days over there but consider this separate not consider the scenarios in same

Report
All responses (
Answers (