we changed the safety time on the item card, how would you update time calculations in the existing PO lines?

(0) ShareShare
ReportReport
Posted on by 350

BC calculated differently for newly added lines (line 2) than for previously existing lines (line 1), see here, after a change for safety time 10D-->1D, and updated SKUs with deletion of existing data:

pastedimage1602055808900v1.png

They are both the same item! 

Translation: 

"Geplantes" -> PLannes Receipt Date

"Erwartetes" --> Expected Receipt Date

My guess is that the safety time is saved somewhere in the PO line and BC does not update this value.

We have a lot of PO lines where we have to update this time calculation. is there a way to to this without manually recreating every PO line and deleting the old ones?

This currently makes our MRP very untrustworthy, alas.

  • Suggested answer
    jerome77 Profile Picture
    on at
    RE: we changed the safety time on the item card, how would you update time calculations in the existing PO lines?

    Hi

    I am not aware of a standard way to proceed here.

    I understand your comment around a general update yes, whereas the fact to change it dynamically when changed at item card level could be a problem. Maybe this is a new agreement, starting with new purchase only. Hard to change all dynamically here.

    I see your point of a possible update button, but does not exist to my knowledge in standard.

    Kind regards

    Jerome

  • benovic Profile Picture
    350 on at
    RE: we changed the safety time on the item card, how would you update time calculations in the existing PO lines?

    thank you for the answer, Jerome!

     

     

    > Next would be to change safety lead time from 10 days to 1, and then create a new line into the purchase order. You expect both lines to be updated?

    Yes, i expect the old line to update to the new Safety time value.

     

     

    I would expect at least one of the following:

    1) immediate recalculation of all PO lines based on the updated value

    2) being  able to adjust this value in the line, directly, like. e.g. warehouse throughput time. (actually preferred method)

    3) have a batch recalculation / updating function per PO, to update lines, like in assembly orders

     

      

    there is _NO_ way of editing this value, through the IU, then?

     

     

    My current solution would be to use rapidstart: open ALL POs, export PO line table, adjust values, reimport.

    I am very unhappy with this, since we are in the process of individually adjusting LT and safety time values - i don't want to do this regularly.

  • Suggested answer
    jerome77 Profile Picture
    on at
    RE: we changed the safety time on the item card, how would you update time calculations in the existing PO lines?

    Hi

    So you mean that you added safety lead time 10 days at item card level, then created a purchase order and added a line.

    Next would be to change safety lead time from 10 days to 1, and then create a new line into the purchase order. You expect both lines to be updated?

    pastedimage1602059351100v1.png

    If you update item card and run the req worksheet for example, system will propose you to cancel and create new purchase order if these are part of planning date run (or reschedule depending on your item card setup).

    Now, if this is manual, then yes no update is done on already entered lines.  Safety lead time is stored at line level (purchase line table)

    pastedimage1602060152656v2.png

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge Winners! 🌸

Congratulations to all our community participants!

Adis Hodzic – Community Spotlight

We are honored to recognize Adis Hodzic as our May 2025 Community…

Kudos to the April Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
YUN ZHU Profile Picture

YUN ZHU 430 Super User 2025 Season 1

#2
Mansi Soni Profile Picture

Mansi Soni 302

#3
Sagar Dangar, MCP Profile Picture

Sagar Dangar, MCP 291

Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans