Hi everyone,
My customer wants to allocate demand forecast per day in a short term period.
Using the new planning optimization feature, there is only one remaining method to reduce demand forecasts : 'transactions - dynamic period'.
So how does it work in case demand forecasts are allocated per day ?
It seems sales order isn't taken into account to reduce demand forecast correctly as if the sales order is not included between to demand forecast dates ...


https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/reduction-keys
If you select Transactions - dynamic period, the forecast requirements are reduced by the actual order transactions that occur during the dynamic period. The dynamic period covers the current forecast dates and ends at the start of the next forecast. In this case, master planning creates planned orders to supply the forecasted demand (forecast requirements). However, when actual order transactions are placed, the forecast requirements are reduced. The actual transactions consume part of the forecasted requirements.