How to assign freight cost to subcontracting work of the production order

(4) ShareShare
ReportReport
Posted on by 42

When trying to assign freight cost to subcontracting work following info is pop upped

Before trying to assign freight costs, the purchase order created for the subcontracting work is received, which created value entry with the entry type Direct Cost and document type  Purchase Invoice.

I have the same question (0)
  • Jun Wang Profile Picture
    8,210 Moderator on at

    looks like the issue is that you post receipt before assigning the freight cost. try to assign one before the line is received.

  • Suggested answer
    Jun Wang Profile Picture
    8,210 Moderator on at

    fortunately, there is a nice function for such situation. you can create a new purchase invoice, add an item charge. click on the qty to assign no., You'll be able to get receipt lines and assign it accordingly. 

  • Suggested answer
    YUN ZHU Profile Picture
    99,559 Super User 2026 Season 1 on at

    Hi, hope the following can give you some hints.

    https://www.dynamicsuser.net/t/how-to-assign-a-item-charge-on-manufacturing-subcontracting-purchase-line/21988

    Thanks.

    ZHU

  • Martin D Profile Picture
    2 on at
    Hi both,
    unfortunately the two answers do not solve the issue because standard code tests that the Work Centre = ''.
     
    FromPurchRcptLine.TESTFIELD("Work Center No.",'');
     
    so obviously NAV/BC believes that any other value would cause an issue... but why, I am unsure.
     
    I cannot find any documentation anywhere.
     
    Any other ideas?
  • Suggested answer
    Dhiren Nagar Profile Picture
    2,898 Super User 2026 Season 1 on at
    Hi,
     
    This is a long due Gap and still not solved.
     
    Basically when you receive material from the Subcontracting order, it does not allow you to add freight cost to it. Better way is to add this as Direct cost to a new work center, use Cost by Unit instead of time and post output, use it during Production order posting.
     

    ✅ Tick the checkbox below to mark the answer as verified, if it helped resolve your question.

    Regards,
    Dhiren.
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,028 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,121 Super User 2026 Season 1

#3
Teagen Boll Profile Picture

Teagen Boll 669 Super User 2026 Season 1

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans