Posted on by 7
hi is there a way of sheduling deliveries in? Nav2018
we have suppliers that only deliver once a month and i need to build this into the lead time and MRP etc
 
i have set up Vendor Receiving calendars for yearly shut downs which works very well is there anything similar for the above
 
Kind Regards
Categories:
  • Suggested answer
    Jun Wang Profile Picture
    Jun Wang 5,453 Super User on at
    Vendor deliveries
    you could create a calendar just for this vendor. the work day will be the days the vendor delivers, the rest of the days will be non work days.
     
     
  • Suggested answer
    YUN ZHU Profile Picture
    YUN ZHU 63,357 Super User on at
    Vendor deliveries
    As far as I know, there is this function in AX, but not in NAV. If necessary, it needs to be customized.

    I hope other experts can give you better suggestions.
     
     
    Thanks.
    ZHU
  • Judy Profile Picture
    Judy Microsoft Employee on at
    Vendor deliveries
    Moved to NAV forum.

Helpful resources

Quick Links

First Dynamics 365 Community Call (CRM Edition)

Don't miss the first D365 Community Call on 7/10!

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 285,480 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,450 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans