Hi Community,
 
Please help advise, How to handle item charges for partial Item receive in NAV?
 
Given the scenario:

I have a purchase order with three lines:

  • 1st line is for item A, and
  • 2nd line is for Item B
  • One line captures item charges allocated across the items by Equally.
Now, we are expecting to receive half of Item A first. Item B will be shipped together with the 2nd portion of Item B.
 
Can you advise how do we do the item charge?
 
Thank you !
Categories:
  • Verified answer
    YUN ZHU Profile Picture
    YUN ZHU 68,586 Super User 2024 Season 2 on at
    How to handle item charges for partial Item receive in NAV?
    I think you're thinking a bit complicated. Create a separate invoice for the item charge.
    Then assign it to the receipt lines. 
    Here it is separated according to each receipt.
     
    Hope this can give you some hints.
    Thanks
    ZHU
  • gdrenteria Profile Picture
    gdrenteria 8,784 Most Valuable Professional on at
    How to handle item charges for partial Item receive in NAV?

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 9th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,326 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 228,166 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans