I finished a production order from released production order using change status as finished with update unit cost. For this system consumed 100 mins as capacity. But if i am checking the Load of same date on Machine center then its showing 100% capacity available. How it is showing the full capacity available as 480 mins?
If your Production Order is finished, it is no longer causing capacity demand for the Work Center. The planned Load of the Machine is 0 (assuming no other Prod. Order Routing Lines for that Machine on that date). If you want to see what has happened before, look at the Machine's Capacity Ledger Entries.