Hi:
The Quantity in the Subcontracting Worksheet is different from that of the one and only Released Production Order.
The order has a Quantity of 5, yet, the worksheet has 5.30605.
Why is there a difference?
Thanks!
John
Hi:
The Quantity in the Subcontracting Worksheet is different from that of the one and only Released Production Order.
The order has a Quantity of 5, yet, the worksheet has 5.30605.
Why is there a difference?
Thanks!
John
Hi Robert:
There are scrap rates in the routing of the finished good. You're right. That must be what "did it".
I just didn't think of that, since the subcontracting is to relate to a subassembly within the BOM.
It's a long story... :)
Thank you, Sir!
John
Is there any SCRAP rates on the Production Order or any of the items (the FG item in the item card)?