MS Project Time Entry Updates To Dynamics PSA

(0) ShareShare
ReportReport
Posted on by

Hello,

If we update the actual hours in MS Project Project which is linked with Dynamics PSA, when publishing it to PSA would that update the time tracking in PSA?


Reason for asking this is Microsoft has only mentioned the below being updated. 

  • Microsoft Project Gantt Chart info imports into the Project Service Automation Work Breakdown Structure screen.
  • Microsoft Project Resource Sheet info imports into the Project Service Automation Project Team Members screen.
  • Microsoft Project Use Usage info imports into the Project Service Automation Project Estimates screen.

I have tried changing the values in MS Project and published it to Dynamics, but it hasn't reflected.

Thanks

*This post is locked for comments

I have the same question (0)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics CRM (Archived)

#1
SA-08121319-0 Profile Picture

SA-08121319-0 4

#1
Calum MacFarlane Profile Picture

Calum MacFarlane 4

#3
Alex Fun Wei Jie Profile Picture

Alex Fun Wei Jie 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans