Production Control - Flushing Principle

(0) ShareShare
ReportReport
Posted on by 200

Hi Dynamics Community

I know the concept behind the flushing principle Start & End.  I set the Flushing Principle to START for all BOM components of a particular FG. Then on Production Start form, I make

sure that Flushing Principle is also selected on Automatic BOM Consumption field. However the picking item lines do not get created unless I also enable the 'Post Picking List Now'

OR I changed the Automatic BOM Consumption to Always.

Please advise if I have missed any setup to ensure that Picking List gets automatically created (no posting yet) upon Starting ProdOrder.

Thanks.

Reign

I have the same question (0)
  • Suggested answer
    Rahul Mohta Profile Picture
    21,032 on at

    could use on BOM line flushing principle as always and also the parameters on production start should create picking list and use principle as always or flushing principle

  • Reign Profile Picture
    200 on at

    Hi Rahul,

    The options available on BOM Lines are Start, Finish, Manual, Available on Location.  What is the difference selecting the flushing principle in BOM Lines versus Released Product Form?

    Also in Production Start form, there is no option to Create Picking List.  There is only Post Picking List option.

    Going back to my concern, may I know which option controls  to ensure that Picking List will be created upon Starting production order but without posting it yet.

  • Suggested answer
    Mariano Melo Profile Picture
    332 Moderator on at

    Hi Reign!

    If you set up in BOM lines, for example "Start", and at start you put the automatic consumption as "Flushing Principle"
    Dynamics will post the journal of that bom line at start. So you can control the backflushing at different times.

    But if you put At Start, or RAF journal "always", dynamics will do the consumption regardless what the bom line has set up.

    if you want to create automatically the journal but not post it, you can start the production order as this image:

    pastedimage1594139133271v1.png

    So dynamics will create the journal, but not post it, because "Post picking list now" is "NO"

    Thanks

  • Verified answer
    Rahul Mohta Profile Picture
    21,032 on at

    under picking list journal section, use automatic BOM consumption as Always and disable post picking list

    this would create/generate picking list for users to pick and then they can confirm /post

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Siv Sagar Profile Picture

Siv Sagar 283 Super User 2025 Season 2

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 213 Super User 2025 Season 2

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 152 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans