web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

No record found.

News and Announcements icon
Community site session details

Community site session details

Session Id :
Small and medium business | Business Central, N...
Unanswered

Element-Wise Standard Cost for New Product

(0) ShareShare
ReportReport
Posted on by 25
Hello,
 
We are using Dynamics 365 and I want to add the standard cost for new finished good item. The only available option is to setup total standard cost but I cannot modify each element (Material, Capacity & OH). Normally material cost is correct as it is getting fetched from Prod BOM but capacity and overheads costs are the areas where I need to play and I have to have specific costs for each of those. I am able to adjust these by changes in Routing times but that is not possible for all products as major change in timing is causing issue in Scheduler. Is there any way to define the element wise standard cost??
For example I want to set the standard cost as per below:
 
Material: 50 per Unit
Capacity: 30 Per Unit
OH: 20 unit
 
Thanks.
I have the same question (0)
  • Shauna Langley Profile Picture
    899 Moderator on at
    Hi,
     
    You would need to setup a routing for the item that has one work centre costed at 0.30p.  See example of work centre below.
     
     
    The routing would then have the following, set the unit cost on the routing line as it is specific for this example.  This work centre could be used for multiple routings as the costing is taken from the routing line and not the work centre itself.
     
    The standard cost worksheet now shows as follows
     
     
    With the split as follows
     
    When you implement that to the item then you will see those values as separate fields on the item card as well.
     
    Hope that helps,
    Shauna
     
     
  • Aamirr Profile Picture
    25 on at
     
    Thanks for the reply and it has sorted out the Capacity cost issue but still I didn't get that how to adjust the OH portion on this. 
    In the above example I set up the standard cost at 1.50 where material cost is pulling from the BOM which is correct, and I assigned 30 Cents as capacity cost. For simplicity purpose let's assume I want to assign difference 12 cents as overhead. Is that possible?
    Indeed, we calculate the OH/KG of our production whereas our Finished goods are in Each weighing from 14G to 12KG but that can be done once I know how to assign specific OH to each item.
    An alternative way would be to have another work center in the same way where I can specify the OH rate in Capacity line but then all entries will fall in Capacity ledger instead of OH ledgers, so I want to avoid it.
     
    Thanks.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,086 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,290 Super User 2026 Season 1

#3
AndrewThomas81 Profile Picture

AndrewThomas81 1,218

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans