Skip to main content

Notifications

Announcements

No record found.

Small and medium business | Business Central, N...
Unanswered

Element-Wise Standard Cost for New Product

Posted on by 25
Hello,
 
We are using Dynamics 365 and I want to add the standard cost for new finished good item. The only available option is to setup total standard cost but I cannot modify each element (Material, Capacity & OH). Normally material cost is correct as it is getting fetched from Prod BOM but capacity and overheads costs are the areas where I need to play and I have to have specific costs for each of those. I am able to adjust these by changes in Routing times but that is not possible for all products as major change in timing is causing issue in Scheduler. Is there any way to define the element wise standard cost??
For example I want to set the standard cost as per below:
 
Material: 50 per Unit
Capacity: 30 Per Unit
OH: 20 unit
 
Thanks.
  • Aamirr Profile Picture
    Aamirr 25 on at
    Element-Wise Standard Cost for New Product
     
    Thanks for the reply and it has sorted out the Capacity cost issue but still I didn't get that how to adjust the OH portion on this. 
    In the above example I set up the standard cost at 1.50 where material cost is pulling from the BOM which is correct, and I assigned 30 Cents as capacity cost. For simplicity purpose let's assume I want to assign difference 12 cents as overhead. Is that possible?
    Indeed, we calculate the OH/KG of our production whereas our Finished goods are in Each weighing from 14G to 12KG but that can be done once I know how to assign specific OH to each item.
    An alternative way would be to have another work center in the same way where I can specify the OH rate in Capacity line but then all entries will fall in Capacity ledger instead of OH ledgers, so I want to avoid it.
     
    Thanks.
  • Shauna Langley Profile Picture
    Shauna Langley 691 Super User 2024 Season 2 on at
    Element-Wise Standard Cost for New Product
    Hi,
     
    You would need to setup a routing for the item that has one work centre costed at 0.30p.  See example of work centre below.
     
     
    The routing would then have the following, set the unit cost on the routing line as it is specific for this example.  This work centre could be used for multiple routings as the costing is taken from the routing line and not the work centre itself.
     
    The standard cost worksheet now shows as follows
     
     
    With the split as follows
     
    When you implement that to the item then you will see those values as separate fields on the item card as well.
     
    Hope that helps,
    Shauna
     
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,214 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans