Planned Purchase order and time fences and coverage and lead time and dates understanding for Microsoft Dynamics 365 Finance and Operations
Planned Purchase order and time fences and coverage and lead time and dates understanding for Microsoft Dynamics 365 Finance and Operations
Delivery date:7/15/2020 (this is the date on PO lines upon firming)
Requirement date but editable
Order date:5/6/2020 (Delivery date - lead time=7/15/2020 - 70=5/6/2020)
Lead time: 70 days
Coverage group: LongCover (154 days) ; warehouse level overrides
Coverage: how many days in future the demand must be fulfilled
Requirement date: (non-editable) 7/15/2020 - to be read as earliest requirement date from pegging
Pegging:
Planned transfer#1: Requirement date, order date and delivery date are 7/15/2020
Planned transfer suggested as demand forecast exists from 7/15/2020 to 12/1/2020
Requirement dates are covered by coverage time fence