Why is there a 1-hour gap between the production order due time and the end of the last operation?

(2) ShareShare
ReportReport
Posted on by 23

Hi everyone,

I'm trying to understand a scheduling behavior in standard Business Central Manufacturing.

Whenever a production order is planned, the last routing operation always finishes exactly one hour before the due date/time of the production order line.

I've already checked the following:

  • Default Safety Lead Time in Manufacturing Setup is empty.
  • Safety Lead Time on the item is empty.
  • The Shop Calendar is configured as a 24-hour calendar (so it is not caused by working hours).
  • There are no Move Time or Wait Time values in the routing.
  • This is standard scheduling without any customizations affecting production planning.

The operation ends one hour before the due date of the production order line. The operation is a outsourced operation with a 24 hour per day capacity. No capacity restrained resource.

Has anyone seen this behavior before or knows where this one-hour offset comes from in the standard application? Is there a setting or part of the scheduling logic that I'm overlooking?

We are running Business Central 28.2 (SaaS).

Any insights would be greatly appreciated.

2026-07-21_11-50-06.jpg
2026-07-21_11-46-44.jpg
I have the same question (0)
  • Suggested answer
    OussamaSabbouh Profile Picture
    18,420 Super User 2026 Season 1 on at
    Hello,
    This is most likely caused by the Shop Calendar ending time, not by Safety Lead Time. In Business Central, the production order Due Date is date-only, and backward scheduling places the last routing operation at the latest available capacity before that date. Since Business Central does not allow 24:00 as a time value, a “24-hour” calendar is often configured with an ending time such as 23:00, which makes the routing end at 23:00 on the previous day. Check the Shop Calendar Working Days and the calculated Work Center Calendar for the subcontracting work center; after correcting the shifts, recalculate the work center calendar and refresh the production order.
    Regards,
    Oussama Sabbouh

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the June Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 677 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 521 Super User 2026 Season 1

#3
Khushbu Rajvi. Profile Picture

Khushbu Rajvi. 306 Super User 2026 Season 1

Last 30 days Overall leaderboard

Featured topics

Microsoft Training Manuals

Product updates

Dynamics 365 release plans