Good day to everyone
Please I need help regarding the Project Module.
In Business Central, I posted usage, I ran WIP, then I posted sales invoice and I ran WIP. But when I checked the chart of account I saw the following result:
2231 WIP Job Costs: -436.96 (Bal. Sheet)
6620 Job Sales: -1,000.00 (P&L)
7620 Job Costs: 436.96(P&L)
2320 Customers: 1,000.00 (Bal. Sheet)
I expected 2231 WIP Job Costs -436.96 (Bal. Sheet) to have zero balance but it is still showing -436.96 balance
Below is the Project Posting group I used:
COST SIDE
| Field |
G/L |
| WIP Costs Account |
2231 |
| WIP Accrued Costs Account |
2231 |
| Project Costs Applied Account |
2231 |
| Item Costs Applied Account |
2231 |
| Resource Costs Applied Account |
2231 |
| G/L Costs Applied Account |
2231 |
| Project Costs Adjustment Account |
2231 |
| G/L Expense Acc. (Contract) |
2231 |
| Recognized Costs Account |
7620 |
SALES SIDE
| Field |
G/L |
| WIP Accrued Sales Account |
6620 |
| WIP Invoiced Sales Account |
6620 |
| Project Sales Applied Account |
6620 |
| Project Sales Adjustment Account |
6620 |
| Recognized Sales Account |
6620 |
Please help me out, I have done all I could do, but I did not get right.