Dear Members,
I am able to a PO into PR when it is in the status of "Draft", but not able to do it when it is in the status of "confirmed". I would like to know whether it is possible to convert the PO into PR when it is in the status of "Confirmed". Is it by system design which prevents me reverting? or is there any setup / options that I need to enable/disable which will allow me to revert back the PO to PR.
Image -1 : Screenshot of the PO when it is in the status of "Draft", which is allowing me to delete the PO and taking the item back to PR.
Image -2 : Screenshot of the PO when it is in the status of "Confirmed", in which the remove option is disabled and not permitting to take the item back to PR.
Please help me out by providing an insight/solution to the issue mentioned.
Thanks,
M Saravanan