MRP - Route Scheduling having a big date difference (overnight vs manual)

Posted on by 5
Hi, community,
 
I am new and we face this situation for a long time.

When running MRP for all items overnight, the result that we see in the Route/Scheduling for just 4 operations is too far, like the Oper. 10 is on 02/09/2023 and the Oper. 40 ends on 08/12/2024 (like 18 months difference) for a route that in total should last less than 4 hours. 
   
The problem is that when I open that PD again and recalculate through /Operations Scheduling (Production Order form), the dates are properly calculated. Is there any particular reason for this?
 

1) Production Order after MRP (OperationsScheduling) > Planned Order > Firming > Production Order
 

 

 
2) But when I go and run the Operations Scheduling again (manually) I see that the Scheduling works perfectly (The example below is in TST).
 


 

 
By the way, the route Information is like this. Resource and Resource Groups are fine as well, calendars are open and enabled for the resources.
  

 
 
Please let me know if you have any suggestions.
 
Thanks,
 
Categories:

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 288,459 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,783 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans