Microsoft Dynamics AX (Archived)

Change resource on production order

(0) ShareShare
ReportReport
Posted on by

Hi,

I have production order that is started and I need to change resource for on operation, so I go to All production orders and under Route I change the resource. Does anyone know what should be my next steps? I believe that I should reschedule my production order? What are consequences of changing the resource on started production order?

Regards

*This post is locked for comments

  • Suggested answer
    Community Member Profile Picture
    on at

    Hi AngelKwiat ,

       Please check this below links it may useful for you,

    technet.microsoft.com/.../aa571840.aspx

    technet.microsoft.com/.../aa571100.aspx

    technet.microsoft.com/.../aa550055.aspx

    Thanks

    Suresh

  • Community Member Profile Picture
    on at

    Hi Suresh potlakayala!

    These links don't really help.

    However I confirmed that I just should reschedule production order.

    Thank you.

    Regards

  • Verified answer
    Fredrik Sætre Profile Picture
    12,644 on at

    There are a couple of ways to change resource on an operation.

    1. Change ProdRoute and Reschedule

    2. Using the Gantt chart

    3. Use the Manufacturing Execition manager feature for replanning.

    2 and 3 require job planning.

  • Community Member Profile Picture
    on at

    Thank you Fredrik!

    Is there any chance you could give more details for 2 ad 3?

    Does it matter which way I will use to change resource?

  • Suggested answer
    Fredrik Sætre Profile Picture
    12,644 on at

    You need to do the job scheduling for the production order.

    2: The Gantt charts are located under Organizational Management and Resources. You can have multiple resources in one Gannt group. Use it and move the jobs between the resources.

    3: Under Production Control > Periodic > Manufacturing Execution you'll find "edit work list". Use that to replan. This will require you to have multiple applicable resources for a route.

    Regarding multiple applicable resources you could try reading up on my blogpost on the matter:

    dynaxtips.com/.../capabilities-setup-2

  • Community Member Profile Picture
    on at

    Thank you Fredrik!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
nmaenpaa Profile Picture

nmaenpaa 2 Moderator

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans