Hi,
I have production order that is started and I need to change resource for on operation, so I go to All production orders and under Route I change the resource. Does anyone know what should be my next steps? I believe that I should reschedule my production order? What are consequences of changing the resource on started production order?
Regards
*This post is locked for comments
Thank you Fredrik!
You need to do the job scheduling for the production order.
2: The Gantt charts are located under Organizational Management and Resources. You can have multiple resources in one Gannt group. Use it and move the jobs between the resources.
3: Under Production Control > Periodic > Manufacturing Execution you'll find "edit work list". Use that to replan. This will require you to have multiple applicable resources for a route.
Regarding multiple applicable resources you could try reading up on my blogpost on the matter:
Thank you Fredrik!
Is there any chance you could give more details for 2 ad 3?
Does it matter which way I will use to change resource?
There are a couple of ways to change resource on an operation.
1. Change ProdRoute and Reschedule
2. Using the Gantt chart
3. Use the Manufacturing Execition manager feature for replanning.
2 and 3 require job planning.
Hi Suresh potlakayala!
These links don't really help.
However I confirmed that I just should reschedule production order.
Thank you.
Regards
Hi AngelKwiat ,
Please check this below links it may useful for you,
technet.microsoft.com/.../aa571840.aspx
technet.microsoft.com/.../aa571100.aspx
technet.microsoft.com/.../aa550055.aspx
Thanks
Suresh
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,240 Super User 2024 Season 2
Martin Dráb 230,149 Most Valuable Professional
nmaenpaa 101,156