Production Wave Automatically Picked (No Work created) if already in Production Input Location

Posted on by 45

Hi,

We are facing an issue since we've updated into D365FO version 10.0.30 with creating picking work for production orders.

When processing the production wave no work is created anymore (before update work was created)for items which are already in the 'Default production input location'. Before work was created for these items with the same pick as put location.

Since the update no work is created anymore, so checking the wave processing log it mentions:
pastedimage1675348841760v1.png

Checked setup for wave processing, but didn't find any setting for this.

Anybody facing the same issue and found a solution?

  • Suggested answer
    Danny Bilodeau Profile Picture
    Danny Bilodeau 4,058 Super User 2024 Season 1 on at
    RE: Production Wave Automatically Picked (No Work created) if already in Production Input Location

    Hello Nick,

    Wave processing work to "Pull" the items from the locations where the item is stocked to the location where the item is needed.  If your item is in the default Production Input Location, the demand-supply equation will simply be resolved without work being required.  You can test by moving this item to another location and releasing again, or by changing that Default Production Input Location to another value.

    The status of <Picked> is probably driven by this setup on the warehouse:

    : pastedimage1675707139914v1.png.

  • NickLaenen Profile Picture
    NickLaenen 45 on at
    RE: Production Wave Automatically Picked (No Work created) if already in Production Input Location

    Hi Danny,

    Wave status is 'held', once released al other items (work is created for items which are not on the 'Default Production Input Location') can be picked. Checking the work creation history log the items which is on hand on the 'Default Production Input Location', are not mentioned at all.

    It seems the deviation is made while processing the wave, which is is also mentioned in the wave processing history (see printscreen in the original post).

    About your question 'Or that BoMLine item was not already in the resource input location?'. There is no resource input location specified, so system is using 'Default Production Input Location' from the warehouse setup. Yes, the item is in this location, but previsously work was still created with the same pick and put location. Problem now is the fact that work is not created and Bom line automatically gets status picked.

  • Suggested answer
    Danny Bilodeau Profile Picture
    Danny Bilodeau 4,058 Super User 2024 Season 1 on at
    RE: Production Wave Automatically Picked (No Work created) if already in Production Input Location

    Hi Nick,

    Don't have 10.0.30 so cant test or reproduce but curious as to what the Production Wave's Status is?  'Picked'?

    If so, did you check that there is no work that was automatically processed.  Or that BoMLine item was not already in the resource input location?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,214 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans