MRP - Multi Select Action Messages

(0) ShareShare
ReportReport
Posted on by 258

When running the planning worksheet, is there a way to quickly multi-select lines to accept action messages or carry out many or all action messages without selecting the accept box? 

  • Suggested answer
    MahGah Profile Picture
    15,613 on at

    Can you please clarify your question a little more

    Do you mean selecting multiple line (which is possible) and then accept message for all of them (which is possible). Or do you mean when you select multiple lines then carry on you do not get the second windows that ask if PO/Production etc should be created (which require development).

  • ahanson Profile Picture
    258 on at

    Select multiple lines and accept for those lines

  • Suggested answer
    MahGah Profile Picture
    15,613 on at

    this may not answer your question but have you tried below in planning worksheet 

    pastedimage1675092416872v1.png

    Select the top one for all or select as many as you want then carry out 

    pastedimage1675092425206v2.png

  • ahanson Profile Picture
    258 on at

    I have tried this, it doesn't perform any actions because I cannot multi-select to accept the action messages.

  • Suggested answer
    MahGah Profile Picture
    15,613 on at

    Sorry, I just realized what you mean. No that is not possible OOTB. By default Action Message is True. Is that not the case for you? If it is True then above message should work.  

  • ahanson Profile Picture
    258 on at

    Where can I find that setting? When I run MRP in our sandbox, it is not automatically selecting all the action messages.

  • Suggested answer
    MahGah Profile Picture
    15,613 on at

    That is by default in BC (part of the base code) 

    If the message is NEW then it is selected if it require change then it is not selected (see below). Do you mean in your Sandbox you have a New but that action did not selected? 

    pastedimage1675093248982v1.jpeg

  • ahanson Profile Picture
    258 on at

    What version are you running? Is this SaaS or on prem?

    Your planning worksheet varies from mine.

    pastedimage1675093690302v1.png

  • Suggested answer
    MahGah Profile Picture
    15,613 on at

    I used one of old pic :) see the new one below 

    That picture helped since it shows has Attention for warning. I know that if it shows attention or other warning then system does not auto select the Action. See mine below. This is because it want planner to review that then select the action. 

    pastedimage1675094037923v1.png

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the August Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 741 Super User 2026 Season 2

#2
YUN ZHU Profile Picture

YUN ZHU 514 Super User 2026 Season 2

#3
AndrewThomas81 Profile Picture

AndrewThomas81 336 Super User 2026 Season 2

Last 30 days Overall leaderboard

Featured topics

Microsoft Training Manuals

Product updates

Dynamics 365 release plans