web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

No record found.

News and Announcements icon
Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Answered

Project Operations- task completion vs estimated effort

(5) ShareShare
ReportReport
Posted on by 26
Hi everyone,
 
I hope you can help me 😊
I have a couple of related queries...
 
1) In Project Operations when the estimated effort is equal to the time tracked against the task it's automatically marking that task as complete. That's not actually helpful for me as the project manager as I need to know when the task is actually done, regardless of if we take longer than expected to perform that task. How can I stop this from automatically happening?
 
2) When I mark a task as complete that has LESS time tracked against it than expected, what happens to that effort? Is there a clever way to review 'unused effort' on the project?
 
3) Lastly, when I do (manually) set a task as completed I'd like that to prohibit any remaining hours being logged to that task. Is there a way to automate this?
 
Many thanks,
Danielle
I have the same question (0)
  • Verified answer
    Juan Simon Profile Picture
    1,026 on at
    Hi Danielle,
     
    Answers:

    1) This is out-of-the-box behavior in Project Operations. The system marks tasks as 100% complete when actual hours equal estimated effort. If more work is needed, increase the estimated effort on the task. This automatically reduces the completion percentage back below 100% until the work is truly finished.  

    2) You can review it by including the Effort Remaining column inside the task grid:

    3) Only through customization at the moment.

    If this helps, please mark this as answered.

    Thanks.

     

    Juan Simon
    www.linkedin.com/in/juan-simon
    https://d365hacks.com/

     
  • Danielle H Profile Picture
    26 on at
    @Juan Simon thank you so much for your reply!
     
    Just a follow up to some of your answers...
     
    question 1- If I increase the estimated effort then I'm not able to track 'overspent' effort. For internal purposes it would be good to know if we're consistently underestimating a certain task. Is there a way to do this that you know of? 
     
    question 2- As we will have a contract tied to our project I don't think I can alter percentage complete. Therefore the task won't show as 100% when the effort isn't all used. Are you aware of any work arounds here?
     
    Many thanks,
    Danni
  • Verified answer
    Juan Simon Profile Picture
    1,026 on at
     
    question 1- If I increase the estimated effort then I'm not able to track 'overspent' effort. For internal purposes it would be good to know if we're consistently underestimating a certain task. Is there a way to do this that you know of? 
     
    Inside Tasks nothing is stopping the PM from changing the effort up or down. Without resorting to a custom solution, you can leverage the Contract and Budget functionalities. When you import tasks from a Project into a contract it stores that 'snapshot there. So if you either consume more or less time, it will show the delta in the actuals as you approve time. And these can be compared. The budget is a similar idea, you create a snapshot, and better than the Contract it shows the delta per line in a better consumable way in my view.
     
    question 2- As we will have a contract tied to our project I don't think I can alter percentage complete. Therefore the task won't show as 100% when the effort isn't all used. Are you aware of any work arounds here? You can alter the percentage complete by completing the task. No actuals are created (unless you use the version that does not use Tim Entries). The work around is automation or a report that allows you to see this more clearly. Otherwise the budget might be you best bet.
     
    I will try and blog about this in the near future to provide options around this. I hope this helps!
  • Danielle H Profile Picture
    26 on at
    Hello @Juan Simon!
     
    Thank you so much for responding again; you have been so helpful and i really appreciate it.
     
    I'm not 100% sure what you mean by 'import tasks into a contract' or utilising the budget as a baseline so if you do blog about this i'd really like to read it :) Is there a way for me to follow you and get notified when you post? I clicked through to your profile but couldn't see anything obvious.
     
    I hope you have a lovely holiday season.
     
    Kindest regards,
    Danielle 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 617

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 461 Super User 2026 Season 1

#3
Syed Haris Shah Profile Picture

Syed Haris Shah 298 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans