Dear All,
I have invoiced multiple PO's with retention of percent 10, as showing below on inquiry form of Project

Now on next invoice, system not showing Total retained amount against same vendor as shown below

The retention ruled i have created as below:

Normally we don't monitor the project progress in %age and need to release retention amount manually.
Anyone have any idea why system is not showing Total retained amount.
Thanks
-Rahat Ali
*This post is locked for comments