what would you suggest if I have a component that will be used twice or more in the same routing. Let's say I have an item that is need 16 times in a BOM. 8 pcs are needed at the first operation and 8 are needed at the fourth operation.
My thoughts:
1)
- BOM: One single line in the BOM with the item and with routing link code 1
- Routing: Assigning routing link code 1 to operation 1 and also to operation 4
2)
- BOM: Two Lines with the same item and each line with quantity 8
- Routing: Assigning routing linke code 1 to operation 1 and routing link code 2 to operation 4.
Does the answer depend on the flushing method?
Thank you very much!