We are using project budgets with budget overruns disallowed. The budget control interval is set to "Project to date." The issue arises when a user posts or commits a cost in a later month (e.g., October), and then posts a new cost in an earlier month (e.g., September). In this case, the system does not recognize the cost that was already consumed or committed in October.
Any one know this issue or there is any setup prevent this to happen?