Pre-encumbrance in budget control

(0) ShareShare
ReportReport
Posted on by 524

Hi,

I'm using budget control in D365.

My setup in budget control as per screenshot below:

pastedimage1613656232583v1.png

I created a purchase requisition, submit to workflow and finally become approved.

Supposed to be since the PR is already approved, the budget funds available will be decreased by the amount of purchase requisition and the status of pre-encumbrance in budget control statistics is Confirmed.

But upon checking, the budget funds available was not reduced by the amount of purchase requisition and the status of pre-encumbrance is still Draft.

Badly needed your help because we are in the implementation stage of budgeting module.

Your replies are highly appreciated.

Thanks.

I have the same question (0)
  • MATTGUO Profile Picture
    22,349 Moderator on at

    Hi,

    For your options, the budget funds available will not be reduced after checking the budget, it will be reduced after the PR is approved.

    You need to check Budget reservations for unconfirmed pre-encumbrances in the configuration.

    Could you give more details about "the status of pre-encumbrance is still Draft"?

  • marypeace Profile Picture
    524 on at

    Hi Mattguo,

    My setup is as follows:

    Budget for unconfirmed pre-encumbrance is not included in the computation of budget funds available.

    pastedimage1614150955685v1.png

    The PR is already Approved.

    pastedimage1614151018147v2.png

    Supposed to be the Budget reservation for unconfirmed pre-encumbrance will be removed since the PR is already approved and must be transferred to Budget reservation for pre-encumbrance and the status of PR must be Confirmed and not Draft as shown below.

    pastedimage1614151333118v8.png

    Since my setup is to allow over budget, the budget funds available must show a negative budget balance because I have no budget for that account.

    pastedimage1614151633325v9.png

    Appreciate your replies.

    Thanks.

  • MATTGUO Profile Picture
    22,349 Moderator on at

    Hi,

    After clicking on the reserve budget funds in PR, the status should be confirmed.

  • marypeace Profile Picture
    524 on at

    Hi Mattguo,

    I used other environment and we don't have to manually click Reserve budget funds, the PR automatically become Confirmed.

    We encounter this issue only in 1 environment but they have the same runtime update with other environment.

    Pls advise.

    Thanks.

  • ToddB Profile Picture
    on at

    Hi Mary,

    If this is still only happening in one environment, I would suggest creating a support incident to have an engineer possibly review traces from both environments.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Siv Sagar Profile Picture

Siv Sagar 303 Super User 2025 Season 2

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 132 Super User 2025 Season 2

#3
Laurens vd Tang Profile Picture

Laurens vd Tang 129 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans