Dear Experts,
Please note that i configured 1 item to use purchase lead time (5 days) then i ticked working days.
Also i created a calendar and linked to a vendor (purchase calendar) which is configured to exclude weekends.
When creating a PR than convert it to a PO, the delivery date is calculated due to the purchase lead time and not considering the calendar which is excluding the weekends.
Your support is highly appreciated in order to solve this issue.
Best Regards,
ER