Payroll Batch did not post to Project Controller
*This post is locked for comments
Announcements
Payroll Batch did not post to Project Controller
*This post is locked for comments
Project Controller > PC Options and Setup can be set up to run FTT automatically when the Time or Time/Dollar batch is released and a project has been entered. If it is not set up to run automatically, then you run it yourself for each period. Maybe the period of the transactions has not been run in FTT.
select pc_status,* from prtran where batnbr = 'xxxxxx'
(where xxxxx = the time entry batch)
If the status is 1, then FTT still needs to be run. If = 2, it has already been run. If blank or 0, no project was entered for that transactions.
Community Member
136
Mohamed Amine Mahmoudi
102
Super User 2025 Season 1
REUser
8