Project Closure Checklist

(4) ShareShare
ReportReport
Posted on by 119
Hello Community!
 
Could you please provide the checklist before closing Time & Material and Fixed Price Projects like it shouldn't have any pending transactions
 
like that do we have any checklist.
 
Thank You. 
Categories:
I have the same question (0)
  • Suggested answer
    Assisted by AI
    H.M.Burhan Profile Picture
    449 Super User 2026 Season 1 on at
    Hi,
     
    Checklist generated by AI. However, I have verified it based on my experience, and it appears to be correct.

    Project Closure Checklist – Dynamics 365 Finance

     

    1. General Project Closure Activities (Applicable to All Project Types)

    Project Setup Validation


    • Confirm project status is updated appropriately:

      • In process → Finished / Completed 

      •  
    • Verify project stages and lifecycle approvals are completed.

    • Ensure project manager approval is received.

    • Confirm no active workflows remain open.

    •  

    Transaction Validation

    Ensure all pending transactions are posted.


    • Review and validate:

      • Hour journals

      • Expense journals

      • Item consumption

      • Vendor invoices

      • Fee journa  

    • Check for unposted journals:

      • Project journals

      • Invoice proposals

      • Pending vendor invoice 

    Financial Review


    • Validate:

      • Project Cost posted correctly

      • Revenue recognized correctly

      • WIP balances cleared where applicable

      •  

    • Reconcile:

      • Project subledger vs General ledger

      • Customer balances

      • Vendor balances

      •  

    • Review exchange rate adjustments for foreign currency projects.


    •  

    Procurement & AP Review


    • Confirm all purchase orders linked to project are:

      • Invoiced

      • Closed/cancelled

      •  

    • Ensure subcontractor/vendor invoices are posted.

    • Validate accrual reversals completed.


    •  

    Resource & Timesheet Closure


    • Ensure all employee timesheets submitted and approved.

    • Confirm no future bookings/resources assigned.

    • Remove remaining forecast assignments if applicable.

    •  

    Document & Audit Readiness


    • Archive:

      • Contracts

      • SOWs

      • Change requests

      • Customer approval 

    • Validate attachments and document references.

    • Export project reports if required for audit.

    •  

    2. Time & Material (T&M) Project Closure Checklist

    Revenue & Billing Validation


    • Ensure all billable transactions are invoiced:

      • Hours

      • Expenses

      • Items

      • Fees

      •  

    • Review invoice proposals for:

      • Missing transactions

      • Write-offs

      • Markups

      •  

    • Confirm final customer invoice posted.


    •  

    Billing Controls


    • Verify no transactions remain with:

      • Chargeable = Yes but not invoiced

      • On-hold invoice statu 

    • Validate sales tax/VAT calculations.


    •  

    WIP & Accruals


    • Clear WIP balances if organization policy requires.

    • Review accrued revenue entries.

    • Ensure revenue recognition completed.

    •  

    Project Estimate Validation


    • Compare:

      • Actual cost vs budget

      • Actual revenue vs forecast

      • Utilization vs planned effort

    Final Financial Close


    • Run project statements:

      • Profitability

      • Consumption

      • Transaction detail

      •  

    • Close project financially.


    •  

    3. Fixed Price Project Closure Checklist

     

    Milestone & Estimation Review


    • Ensure all milestones completed and approved.

    • Validate completion percentage.

    • Confirm estimate project updated fully.

    •  

    Revenue Recognition


    • Verify revenue recognition entries posted:

      • Completed contract method OR

      • Percentage of completion metho 

    • Confirm no deferred revenue remains incorrectly.


    •  

    On-Account Transactions


    • Validate all on-account/customer advances settled.

    • Ensure retention amounts processed if applicable.

    •  

    Estimate Elimination


    • Run estimate process one final time.

    • Verify:

      • Cost-to-complete

      • Accrued revenue

      • Estimated profit

      •  

    • Confirm estimate status finalized.

    •  

    WIP & Balance Review


    • Ensure:

      • WIP cleared appropriately

      • No remaining committed cost

      • No pending procurement

    Final Invoice Validation


    • Confirm final milestone invoice issued.

    • Validate contract value fully billed.

    • Review retention release invoices if used.

    •  

    4. Recommended Reports Before Closure

    In Microsoft Dynamics 365 Finance review:


    • Project statement

    • Profit and loss by project

    • WIP report

    • Open transaction report

    • Hour utilization report

    • Estimate report

    • Committed costs report

    • Customer aging

    • Vendor aging

    • Revenue recognition report

    •  

    5. Recommended System Controls Before Marking Project Completed

    Suggested Validation Rules


    • No open purchase orders

    • No unposted journals

    • No pending invoice proposals

    • No active forecasts

    • No remaining committed costs

    • No draft timesheets/expenses

    •  

    ••Project balance reconciled to GL


    Cheers,
    Burhan

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Launch!

Jump in, show your community spirit, and win prizes!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the May Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Abhilash Warrier Profile Picture

Abhilash Warrier 628 Super User 2026 Season 1

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 501 Super User 2026 Season 1

#3
Subra Profile Picture

Subra 437

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans